Description
UPDATE:
- Project Complete: The main replacement project is complete.
Project Overview
TVWD will be:
- Replacing about 1,350 feet of 6-inch cast iron water main under SW Skyhar Dr., from SW Oleson Rd. to SW Obrien St., with 8-inch ductile iron main.
- Installing new or relocating fire hydrants.
Water mains are underground pipes in the street that carry treated drinking water from a water treatment plant to homes and businesses within TVWD's water service area.
Project Map
View a map of the worksite and the project's public outreach area.
General Impacts
During construction, there will be noise, dust, and vibrations. Watch our short video to learn more about what to expect.
Work Schedule- Weekdays between 8 a.m. and 4 p.m.
- Large equipment in the area
- A drone may be used to document progress
- Temporary driveway access delays and parking restrictions
- Temporary lane closures with traffic control and flaggers
- Sidewalks will stay open along the project route
- Mail, deliveries, and garbage collection will continue as usual
- Water service shutoffs may occur as part of this project. Impacted customers will receive at least 48 hours’ notice.
Construction Process
Phase 1: Install Sections of New Water Main and Install/Relocate Fire Hydrants
- Crews will cut the pavement and dig a trench.
- New main will be installed in sections.
- The trench will be backfilled and covered with temporary asphalt.
- The new main will be tested to make sure it’s working properly.
- Fire hydrants will be installed or relocated.
Phase 2: Reconnect Water Service Lines
- Dig near each customer’s water meter to locate their water service line.
- Disconnect each customer's service line – or the smaller pipes that branch off from the main and deliver water directly to homes and businesses – from the old main.
- Connect each customer's service line to the new main.
- Temporarily restore the area with an asphalt patch.
This phase will require a one-hour water service shut off to customers in the immediate area of the main installation. Impacted customers will receive an email notification in advance. TVWD will also knock on each customer's door before temporarily shutting off water service.
Phase 3: Connect New Main to Water System and Disconnect Old Main
- Dig into the street to locate the new main.
- Connect the newly installed main to the water system.
- Dig into the street to locate the old main.
- Disconnect the old main from the active water system.
- Cap off both ends of the old main.
- Leave the old main in place underground.
- Temporarily restore the area with an asphalt patch.
This phase will require a four-to-six-hour water service shut off to customers in the immediate area of the main installation. Impacted customers will receive an email, text, automated phone call, and doorhanger at least 48-hours in advance of the shut off.
Phase 4: Permanent Paving (by Contractor)
- Remove the existing road surface using a heavy machine with a rotating drum and sharp blades.
- Clean and prepare road surface.
- Spread and compact hot asphalt evenly using paving machines and workers.
- Apply a light dusting of sand to ensure safety and durability as the asphalt cures and settles.
Project Benefits
Sections of the current water main under Skydar Drive were installed in the late 1970s. Based on its age, condition, material, and leak history, it was prioritized for replacement.
The project will improve the water system in this area by:
- Boosting reliability: The new main will be stronger and less likely to leak, helping prevent service interruptions.
- Improving water flow: The larger, modern main can move more water at higher pressure to homes and hydrants in the neighborhood.
- Enhancing fire protection: Firefighters will have better access to water for emergency response.