209th & Farmington Facility

Project Type:
Water source expansion/improvement
Project Status: 
Under Construction
Location: 
20925 SW Farmington Rd
Beaverton, OR 97007

Project Virtual Open House

Please visit our virtual open house to learn more about this project, the project team, and what the 209th & Farmington site will be like after construction. 

Virtual Open House

Current Updates

We are entering the final stages of project completion and facility startup. Over the last few weeks, there has been a flurry of activity to finish the installation of all of the interior electrical and mechanical equipment. The contractor recently completed a portion of the electrical startup, which includes testing all of the equipment within the facility to make sure the facility is operating properly.

  • Over the next few weeks,  the contractor will be filling the pipe to the west of the site with water and testing it to make sure it is safe to drink. Once that is complete, there will be a final day on-site for the contractor to complete all interior equipment tests.
  • Final site cleanup and installation of a light pole on Farmington Road remain the major items to be completed this month.

Last Updated: Feb. 12, 2024

Construction During Site Building

Changes to site construction will change the level of noise, dust, and vibration experienced by neighbors.

  • Vibration and light shaking is likely throughout the early part of this phase 
  • Significant noise coming from the project site, though exact impacts can be difficult to decipher due to the traffic noise on Farmington Road
  • Noise from back-up beepers, tools, and equipment will increase 

How Can I Stay Informed?

Construction Impacts

Impacts during construction will be mostly noise, vibration, and dust generated by construction equipment on the site. 

  • Traffic circulation near the intersection of 209th Ave and Farmington Road will be impacted by trucks and equipment accessing the site. One or more lanes of these roads are expected to be closed while site improvements are made. 
  • The construction hours will most likely be 7 a.m. to 7 p.m. Monday through Friday, with the possibility for hours to shift based on extreme weather or to prevent significant traffic impacts.

Updated July 19, 2022

Proposed Site Aerial View
Proposed Site Farmington View
Proposed Site 209th View
Site Section View
Public Outreach Target Area